Definition

A cost that cannot be recovered, whatever the firm decides next. Because no choice can change it, a firm ignores it when deciding what to do next.

Small vs large sunk cost

  • Delivery truck: The truck can be resold → Small sunk cost → entry is low-risk.
  • Power plant: Cannot be moved or used for anything else → its resale value falls with the market → large sunk cost → entry is very risky.

The size of the sunk cost determines how high the entry barrier is. This is why free entry fails in electricity generation.

SR vs LR

  • SR: FC is sunk: paid whether the firm produces or shuts down → drops out of the decision → compare PP vs AVCAVC.
  • LR: all factors are variable → no cost is sunk yet → compare PP vs ATCATC.
Electricity

Once a plant is built, its capital cost is sunk. The plant keeps running as long as the price covers its fuel and CO2 costs (P≥AVCP \ge AVC), even if it never recovers the capital cost.

Links: Shutdown Rule, Perfect Competition, W1.2 Organization of the Electricity Sector