W3.2 Economics of Generation Investment

Created

Key points

  • Build vs run: building compares AC=Cfh+CvAC = \frac{C_f}{h} + C_v at expected hours; running compares VC only (fixed cost sunk)
  • Break-even hours split demand. E.g. base (low CvC_v, coal), mid (CCGT), peak (low CfC_f, OCGT)
  • Energy-only market: scarcity price spikes pay for capacity; optimum at LRMC = VoLL → security of supply < 100%
  • Price cap too low → missing money → under-investment → capacity mechanisms
  • Also: regulatory and other uncertainty, risk aversion (risk asymmetry), investment cycles, reserve capacity as a public good
  • Existing fossil plants’ sunk capital raises the CO2 price needed for new renewables